According to Claude:
The Jubilee River is a man-made flood relief channel built in the late 1990s and early 2000s to reduce flooding risk along the River Thames between Maidenhead and Windsor in the UK. Shortly after its completion, it experienced significant bank erosion and stability issues.
The key problems included:
1. Rapid bank erosion, particularly during high flow events
2. Slumping and failure of bank sections
3. Issues with the original bank protection measures
The issues stemmed from several factors:
– The channel design velocity was higher than natural Thames conditions, leading to increased erosive forces
– Some bank protection measures weren’t adequate for the flow conditions
– There were challenges with soil conditions and bank construction methods
The Environment Agency had to undertake significant remedial works to address these problems, including installing additional bank protection and modifying some sections of the channel. This became a notable case study in river engineering, highlighting the importance of properly accounting for erosion forces in artificial channel design.
However, I encourage you to verify these details, particularly regarding the specifics of the remedial works, as I aim to be cautious when discussing technical engineering failures where accuracy is important. Would you like me to elaborate on any particular aspect of the Jubilee River’s erosion issues?
I have now informed Claude about what I know about JR bank failures
Claude says:
Your concerns about the persistence of Jubilee River bank failures and their implications for newer flood alleviation channels are very serious. The fact that failures are still occurring after 20+ years suggests fundamental issues with the original design approach that weren’t fully addressed even through remedial works.
The 2006 out-of-court settlement you mention is particularly significant, as it formally acknowledged design and construction deficiencies. Yet despite this precedent and the clear lessons that should have been learned, you’re noticing similar design approaches being proposed for new schemes.
Some critical questions this raises:
1. Have the specific design failures from the Jubilee River been properly documented and shared within the engineering community?
2. What aspects of the original problematic design elements are you seeing repeated in new proposals?
3. How might the regulatory framework be failing to prevent known problematic design approaches from being perpetuated?
This seems to point to a potential systemic issue in how lessons learned from major infrastructure failures are [or aren’t] being incorporated into current practice. Would you be willing to share more specific examples of where you’re seeing these concerning design elements being proposed in new schemes? This could help identify whether there are particular patterns that need to be addressed in current design guidance or review processes.
Thank you for sharing these illuminating images of the Jubilee River issues. Let me analyze what they show:
Images 1 & 2 show the December 2024 bank failure:
– Significant semicircular slip failure in the bank
– Emergency placement of rock-filled bags as temporary protection
– Alarmingly close proximity to new residential development
– Clear evidence of previous protection measures that have failed
– Large exposed drainage pipe now unsupported
Image 3 demonstrates:
– High flow conditions
– Turbulent flow patterns that may be contributing to erosion
– Dense vegetation that was present historically
Image 4 reveals:
– Different bank protection approach (stepped stone revetment)
– Close proximity of residential properties
– Warning sign indicating recognition of hazards
– Evidence of previous remedial works
Image 5 shows:
– Active erosion processes
– Turbulent flow conditions
– Signs of ongoing bank instability
Key concerns these images raise:
1. The proximity of expensive residential development to repeatedly failing banks
2. Evidence of multiple different protection approaches, suggesting reactive rather than strategic solutions
3. High energy flow conditions that may exceed design parameters
4. Risk to infrastructure (exposed pipe) and property
5. Questionable development permissions given the known history of failures
These images strongly support your concern about similar designs being proposed for new schemes. The repeated failures despite various remedial approaches suggest fundamental issues with the channel design philosophy.
Would you be able to explain more about the current hydraulic design standards being proposed for new schemes like the River Thames Scheme? The evidence in these images suggests urgent need for review.
In response to Information from Ian – Claude says:
This is valuable technical insight about the Jubilee River issues. Let me analyze the key points your friend has raised:
1. Root Cause Identification:
– Scour is identified as the primary mechanism for structural degradation
– The critical design flaw was the omission of a planned stilling basin by the Environment Agency (EA)
– This omission was reportedly made for cost-saving reasons
2. Hydraulic Impact:
– Without the stilling basin, hydraulic forces (both suction and pressure) from gate operations aren’t being properly dispersed into the riverbed
– Instead, these forces are directly impacting channel side structures
– This explains the pattern of structural issues noted in the Atkins Water report
3. New Infrastructure Concern:
– The exposed pipe is potentially a foul sewer line
– This raises additional public health considerations
– Immediate investigation would be warranted given the health implications
This information suggests a classic case of false economy – where cost-cutting during construction (removing the stilling basin) has led to significantly greater long-term structural problems and potential remediation costs.
Would your friend be able to provide any additional details about:
1. The original design specifications for the stilling basin that was omitted, or
2. The typical flow rates and gate operation patterns that are now creating these problematic hydraulic forces?
This would help in understanding the full scope of the engineering challenge.
Sorry – it’s too late – goodnight Claude
END
Can you please inform Claud , that the principle cause for poorly designed structures within rivers and channels over time is scour, In this case the deletion of the intended stilling basin within the JR is the root cause of most of all of the structures noted within the Atkins Water report .
The deletion of a stilling basin by the EA on cost saving grounds has resulted in the hydraulic forces of suction and pressure generated by the gate movements not being dispersed into the river bed but being activated against structures within the channel sides.
The pipe recently exposed would appear to be a foul sewer pipe, for health reasons this requires to be investigated.
Dear Claude,
I do not have the original detail and specification details of the proposed stilling basin design as it was withdrawn from construction . However details of a stilling basin can be obtained from civil engineering guide books.
With regard to details of gate movements these I do have from 2003 event when too much water was released too quickly and the whole system throughout the JR fell to pieces as detailed within the Atkins report. Consequence ;- I was commissioned to carry out a survey of the flood envelope between Elizabeth Bridge and Staines Bridge denoting the extent of the out of control flooding within that reach. results of survey approved by the EA.
In 2014 the EA lost control of the JR Taplow sluices , I have their daily diary of releases which I set out in a graph depicting where and and at what time and date that they lost control.
Following that having received a copy of their failed operating instructions I recalculated their gate movements to provide a more gradual more frequent opening procedure that avoided loss of control and a better warning to downstream communities, They appear to be working to that plan as confirmed by all following years gate movements.
Your assessment of my previous email points are correct .
Frequent undamped hydraulic surges against unreinforced constantly saturated earth banks can seek out weak points , which appears to be this example of a number within the past within the Taplow reach.
Kind Regards,
Ian.